Task / Description Slow   Ave   Fast    Units
 Windows, Timber Frames for Bricklaying 1.1  0.5  0.1   hrs/no
 Windows, Drill, Screw & Plug extra over 0.3  0.1  –    hrs/no
 Door Frames, Softwood, 1.0-3.0m2 –   0.2  –    hrs/no
 Door Frames, Softwood, 3.0-7.0m2 0.5  0.4  –    hrs/no
 Door Frames, Softwood, 7.0-10.0m2 1.2  0.8  –    hrs/no
 Door Frames, Hardwood, 1.0-3.0m2 –   0.3  –    hrs/no
 Door Frames, Hardwood, 3.0-7.0m2 0.6  0.3  –    hrs/no
 Door Frames, Hardwood, 7.0-10.0m2 1.4  1.0  –    hrs/no
 Erect Water Tank Platform –   2.3  –    no/hr
 Fix Studding For Bath –   0.1  –    hrs/m
 Cut Access Hatch –   0.3  –    no/hr
 Floor Joists, under 3m 9.0  9.6  11.6   no/hr
 Floor Joists, 3.0-4.5m 6.8  7.2  9.7   no/hr
 Floor Joists, 4.5-6.0m 5.5  5.8  7.3   no/hr
 Ceiling Joists, under 3m 12.8  14.0  14.7   no/hr
 Ceiling Joists, 3.0-4.5m 10.8  12.1  12.6   no/hr
 Ceiling Joists, 4.5-6.0m 9.6  10.8  11.1   no/hr
 Ceiling Joists, Notch to Beams 20.0  25.0  28.5   no/hr
 Ceiling Joists, Pack Joist Ends 20.1  23.8  26.3   no/hr
 Ceiling Joists, Nailing Joists together –   23.0  –    m/hr
 Ceiling Joists, Bolting Joists Together –   12.6  –    m/hr
 Floor Boards, Butt Jointed –   1.7  –    m2/hr
 Floor Boards, T&G Boards, under 75mm wide –   3.4  –    m2/hr
 Floor Boards, T&G Boards, 75-100mm wide –   3.8  –    m2/hr
 Floor Boards, T&G Boards, 100-125mm wide –   4.2  –    m2/hr
 Floor Boards, T&G Boards, 125-150mm wide –   5.5  –    m2/hr
 Plywood Sheeting, Butt Jointed, nailed –   9.1  10.2   m2/hr
 Plywood Sheeting, Butt Jointed, screwed –   4.1  4.8   m2/hr
 Plywood Sheeting, T&G Jointed, nailed –   8.3  9.1   m2/hr
 Plywood Sheeting, T&G Jointed, screwed –   4.0  4.6   m2/hr
 Chipboard Sheeting, Butt Jointed, nailed –   10.0  11.5   m2/hr
 Chipboard Sheeting, Butt Jointed, screwed –   5.1  5.8   m2/hr
 Chipboard Sheeting, T&G Jointed, nailed –   9.3  9.1   m2/hr
 Chipboard Sheeting, T&G Jointed, screwed –   5.5  5.9   m2/hr