Lifts and Escalators


Escalators Installation

Task / Description Slow   Ave   Fast    Units
 Truss type, Overall Installation (excl arch finishes) 14.0  12.0  11.0   wks
 Truss type, Manufacture, test and deliver –   60.0  48.0   wks
 Truss type, Phase A assemble truss , position/level –   1.0  –    wks
 Truss type, Stop-Work for surrounding finishes 8.0  6.0  4.0   wks
 Truss type, Phase B decking and glazing etc –   5.0  –    wks
 Truss type, Phase C performance testing –   2.0  –    wks
 Truss type, Phase D full load testing –   2.0  –    wks
 Truss type, Phase E final test and inspection –   2.0  –    wks

 

Lift Installation

Task / Description Slow   Ave   Fast    Units
 Hydraulic Lift, Install 2 to 3 storeys –   3.0  –    wks/floor
 Hydraulic Lift, Install 4 storeys and above –   2.0  –    wks/floor
 Hydraulic Lift, Testing allow 2 wks plus –   1.0  –    day/floor
 Standard Lift, Manufacture, test and deliver –   12.0  –    wks
 Non-Standard Lift, Manufacture, test and deliver 75.0  65.0  52.0   wks