Task / Description | Slow | Ave | Fast | Units |
Setup small 2 hole system | 10.0 | 8.0 | 6.0 | days |
Setup large 15 hole system | – | 21.0 | – | days |
Calculate system times per pump | – | 2.5 | – | days/pump |
Setup Recharge System | – | 3.5 | – | days/pump |
Project Management, Estimating, Scheduling, Takeoff and Bid Management
Task / Description | Slow | Ave | Fast | Units |
Setup small 2 hole system | 10.0 | 8.0 | 6.0 | days |
Setup large 15 hole system | – | 21.0 | – | days |
Calculate system times per pump | – | 2.5 | – | days/pump |
Setup Recharge System | – | 3.5 | – | days/pump |