Plasterboard

Task / Description Slow   Ave   Fast    Units
 Boarding to Plaster dabs 3.6  4.0  5.5   m2/hr
 Boarding to Stud-work/Metal Lathes 4.0  5.0  6.7   m2/hr
 Boarding 12mm nailed to studding –   12.5  –    m2/hr
 Boarding 19mm nailed to studding –   16.5  –    m2/hr
 Tape, Jointing and Sanding –   0.1  –    hrs/m