Task / Description Slow   Ave   Fast    Units
 Fix 0.5m2 Stones to Metal Support Frame 5.6  7.0  7.8   m2/day
 Fix 0.5-0.75m2 Stones to Metal Support Frame 7.2  9.0  10.1   m2/day
 Fix 0.75-1.0m2 Stones to Metal Support Frame 6.9  8.7  9.7   m2/day
 Fix Complex Stonework to Metal Support Frame –   1.8  –    m2/day
 Fix Curved Stone Cladding 6.9  8.0  9.2   m2/day
 Fix Stone Edge Beams/Window Reveals –   2.3  3.2   m2/day
 Fix Stone Soffits –   4.0  –    m2/day
 Stone Floors 6.9  10.4  12.2   m2/day
 Granite Wall Panels, First Fix –   1.3  –    m2/hr