Water Proofing

Task / DescriptionSlow  Ave  Fast   Units
 Asphalt coatings, horizontal surfaces3.5 4.2 5.8  m2/hr
 Asphalt coatings, vertical surfaces1.2 1.7 2.2  m2/hr
 Bituminous Brushed application, 2 coats4.8 5.0 6.3  m2/hr
 Bituminous Brushed application, 3 coats3.3 3.5 4.4  m2/hr
 Bituminous Sheets, horizontal surfaces3.8 4.0 4.8  m2/hr
 Bituminous Sheets, vertical surfaces3.3 3.5 4.2  m2/hr
 Polythene Sheets, horizontal surfaces–  20.0 –   m2/hr
 Bentonite Sheets, horizontal surfaces18.7 25.0 31.3  m2/hr
 Bentonite Sheets, vertical surfaces11.2 15.0 17.3  m2/hr
 Epoxy Based application, 1 coat–  75.0 –   m2/hr
 Epoxy Based application, 2 coat–  38.0 –   m2/hr