Pile Cutting Back

Task / Description Slow   Ave   Fast    Units
 Concrete Pile Caps, 50-300mm deep and 0.6m dia 0.6  –   0.3   hrs/no
 Concrete Pile Caps, 300-750mm deep and 0.6m dia 1.5  –   0.4   hrs/no
 Concrete Pile Caps, > 750mm deep and 0.6m dia 1.8  –   0.8   hrs/no
 Concrete Pile Caps, 50-300mm deep and 1.1m dia 1.9  –   0.8   hrs/no
 Concrete Pile Caps, 300-750mm deep and 1.1m dia 2.5  –   1.1   hrs/no
 Concrete Pile Caps, > 750mm deep and 1.1m dia 4.2  –   2.3   hrs/no
 Concrete Pile Caps, 50-300mm deep and 2.5m dia 9.2  –   8.2   hrs/no
 Concrete Pile Caps, 300-750mm deep and 2.5m dia 10.1  –   9.5   hrs/no
 Concrete Pile Caps, > 750mm deep and 2.5m dia 11.5  –   10.2   hrs/no
 Concrete, Cutting Slabs, 5-25m deep –   15.2  –    m/hr
 Concrete, Cutting Slabs, 25-50m deep –   11.5  –    m/hr
 Concrete, Cutting Slabs, 50-75m deep –   6.7  –    m/hr
 Concrete, Cutting Holes, coring machine –   0.2  –    m3/hr
 Concrete, Cutting Back to expose couplers 0.7m slab –   2.5  –    m/day