Rail Trackwork

Task / Description Slow   Ave   Fast    Units
 FST Floating Track Slab, side restraints 9.6  –   –    m/day
 FST Floating Track Slab, resin pads 10.2  –   –    m/day
 FST Floating Track Slab, slab units 10.6  –   –    m/day
 PCBT – Pre-cast Concrete Block Track, in Bored Tunnels 17.1  41.0  –    m/day
 PCBT – Pre-cast Concrete Block Track, in Cut and Cover Tunnels –   35.0  –    m/day
 PCBT – Pre-cast Concrete Block Track, in Station Tunnels –   35.0  –    m/day
 IST – Isolated Slab Track, in Bored Tunnels –   20.0  –    m/day
 IST – Isolated Slab Track, in Cut and Cover Tunnels –   34.0  –    m/day
 IST – Isolated Slab Track, in Station –   29.0  –    m/day
 FST – Floating Slab Track, in Station 3.6  4.6  5.7   m/day
 Ballasted Track, in Mainline 57.0  71.0  115.0   m/day
 Ballasted Track, in Depot –   28.0  –    m/day
 Non-Ballasted Track, in Depot 8.5  12.8  17.4   m/day
 Embedded / Paved Track, in Depot –   71.0  –    m/day
 Heavy Maintenance / Train Wash Track, in Depot –   29.0  –    m/day
 Maintenance Pit, in Depot –   52.0  –    m/day
 Siding Trackwork, in Depot –   38.0  –    m/day