FST Floating Track Slab, side restraints | 9.6 | – | – | m/day |
FST Floating Track Slab, resin pads | 10.2 | – | – | m/day |
FST Floating Track Slab, slab units | 10.6 | – | – | m/day |
PCBT – Pre-cast Concrete Block Track, in Bored Tunnels | 17.1 | 41.0 | – | m/day |
PCBT – Pre-cast Concrete Block Track, in Cut and Cover Tunnels | – | 35.0 | – | m/day |
PCBT – Pre-cast Concrete Block Track, in Station Tunnels | – | 35.0 | – | m/day |
IST – Isolated Slab Track, in Bored Tunnels | – | 20.0 | – | m/day |
IST – Isolated Slab Track, in Cut and Cover Tunnels | – | 34.0 | – | m/day |
IST – Isolated Slab Track, in Station | – | 29.0 | – | m/day |
FST – Floating Slab Track, in Station | 3.6 | 4.6 | 5.7 | m/day |
Ballasted Track, in Mainline | 57.0 | 71.0 | 115.0 | m/day |
Ballasted Track, in Depot | – | 28.0 | – | m/day |
Non-Ballasted Track, in Depot | 8.5 | 12.8 | 17.4 | m/day |
Embedded / Paved Track, in Depot | – | 71.0 | – | m/day |
Heavy Maintenance / Train Wash Track, in Depot | – | 29.0 | – | m/day |
Maintenance Pit, in Depot | – | 52.0 | – | m/day |
Siding Trackwork, in Depot | – | 38.0 | – | m/day |