Timber Frames

Task / Description Slow   Ave   Fast    Units
 Roof Trusses –   1.3  –    no/hr
 Wall Plates –   2.7  –    m/hr
 Roof Rafters –   1.2  –    m/hr
 Ceiling Joists –   32.1  –    m/hr
 Roof Carcass, Common Rafters, under 3m 18.2  20.0  21.7   no/hr
 Roof Carcass, Common Rafters, 3-6mm 13.3  16.6  18.2   no/hr
 Roof Carcass, Common Rafters, over 6m 14.1  15.6  16.1   no/hr
 Roof Carcass, Jack Rafters, under 3m 18.8  20.1  21.7   no/hr
 Roof Carcass, Jack Rafters, 3-6mm 10.4  16.1  16.6   no/hr
 Roof Carcass, Purlins, under 3m 5.1  5.4  5.8   no/hr
 Roof Carcass, Purlins, 3-6mm 4.3  4.8  5.1   no/hr
 Roof Carcass, Purlins, over 6m 3.5  4.3  4.6   no/hr
 Roof Carcass, Binders, under 3m 5.7  6.6  7.6   no/hr
 Roof Carcass, Binders, 3-6mm 2.1  2.3  2.5   no/hr
 Roof Carcass, Binders, over 6m 1.3  1.5  1.6   no/hr
 Roof Carcass, Hangers, under 3m 8.2  9.0  9.6   no/hr
 Roof Carcass, Collars under 3m 7.6  8.0  9.1   no/hr
 Roof Carcass, Collars 3-m 6.5  7.4  8.3   no/hr
 Roof Carcass, Ridge Boards under 3m 12.0  13.1  15.3   no/hr
 Roof Carcass, Cut Rafter Feet to line 142.0  166.0  175.0   no/hr
 Roof Soffits, Softwood, nailed –   9.2  –    m/hr
 Roof Soffits, Softwood, screwed –   3.9  –    m/hr
 Roof Soffits Asbestos, under 300mm nailed –   9.1  –    m/hr
 Roof Soffits Asbestos, under 300mm screwed –   3.8  –    m/hr
 Roof Soffits, Asbestos, over 300mm nailed –   3.5  –    m/hr
 Roof Soffits, Asbestos, over 300mm screwed –   1.3  –    m/hr
 Roof Facia Panels, Softwood 5.1  7.2  9.3   m/hr
 Roof Facia Panels, Asbestos 1.3  2.5  3.9   m/hr
 Roof Facia Panel Studding, nailed 7.3  8.1  9.0   m/hr
 Roof Facia Panel Studding, screwed 4.6  5.2  5.8   m/hr
 Roof Facia Panel Studding, bolted to beams 5.4  5.9  6.6   m/hr
 Roof Works, Fix Herringbone Strutting –   5.1  –    m/hr
 Roof Works, Fix Firing Strips –   25.0  –    m/hr
 Roof Works, Fix Drip/Tilt Filleting –   20.5  –    m/hr